Direct answer: Chinese national holidays — mainly Chinese New Year (late January to mid-February) and the October National Day golden week — can slow factory output and freight in the weeks around the dates, plus a post-holiday ramp-up period. This is a general industry pattern, not a PunchPowerUp-specific commitment, and we don’t have a published figure for exactly how many extra days to add. Our published lead-time figures (roughly 20-40 working days depending on order type) remain planning figures, not delivery guarantees — build extra buffer if your order window touches either holiday period.

Which Chinese holidays actually affect production and shipping

These dates are public national holidays, not internal PunchPowerUp data — worth saying upfront so it’s clear what’s a calendar fact and what’s specific to us:

  • Chinese New Year (Spring Festival). Falls on a different date each year, typically late January to mid-February, based on the lunar calendar. This is the longest and most disruptive period for manufacturing across many industries in China, not just boxing gear.
  • National Day golden week. October 1-7, fixed every year. Shorter than Chinese New Year, but still a full-week shutdown across much of the manufacturing sector.
  • Labour Day. Early May, typically a shorter break (a few days), with a smaller impact than the two holidays above.

If your event, delivery date, or production window falls near any of these, that’s worth flagging when you request a quote — not something we’ll necessarily catch automatically from a date alone.

How these periods typically affect factories and freight — before, during, after

This is a general pattern across manufacturing in China, not a PunchPowerUp-specific policy: factories commonly slow down in the run-up to a major holiday as staff prepare to travel, close for the holiday itself, then take a period afterward to return to normal output as workers come back and production schedules reset. We don’t have a published figure for exactly how many days each phase typically adds — it varies by factory and by which holiday — so treat it as a real risk to plan around rather than a fixed number of extra days. Freight and customs processing can also see backlogs in the weeks immediately before and after, independent of factory closures themselves.

None of this is a claim about exactly how our specific production partners handle it — it’s the general shape of the calendar risk, and it’s worth planning around regardless of which supplier is involved.

Where our published lead-time figures sit against that calendar

For custom championship belts, the published planning figures are: roughly 20 working days for a sample or one-belt order, 30 working days for a standard bulk order, and roughly 40 working days during peak periods. Rush production isn’t supported at any quantity. All of these are planning figures, not delivery guarantees, and production time is calculated separately from shipping and customs time.

One thing worth being precise about: our internal records don’t explicitly tie that “peak season” 40-day figure to Chinese New Year or National Day specifically — it may reflect general order-volume fluctuation rather than a fixed calendar window. If your order timeline overlaps either holiday, treat the standard 30-40 day range as a starting point rather than an exact answer, and ask us to confirm the specific status against your dates when you request a quote.

The Smart Boxing Machine works differently: it dispatches within 24 hours of order confirmation, subject to stock — that’s a retail, ships-from-stock model rather than a made-to-order production run, so it isn’t exposed to the same kind of holiday production-scheduling risk in the same way a custom belt order is. We don’t have published data on whether restocking that inventory is affected by these holidays, so if you’re ordering in volume around a holiday window, that’s worth confirming rather than assuming either way.

Working backward from your event or delivery date

The planning logic is the same regardless of the specific dates involved: start from the date you actually need the order, then work backward.

Step What to subtract
Your event or delivery date —
Shipping and customs time Varies by destination; confirmed on your quote, not a fixed number here
Production time ~20-40 working days depending on order type and season (see above)
Buffer for a holiday overlap Add extra time if any part of the above touches Chinese New Year, National Day, or Labour Day

If working backward from your date lands close to, or inside, one of these holiday windows, that’s the point to add buffer rather than assume the standard planning figures still apply cleanly.

What a tight production window taught us

On one order, a batch of 10 custom belts had to go back into production after a supplier quality issue, and the reworked batch was rushed to make up time. The deeper lesson from that case isn’t really about the specific fault — it’s that when a production window is already tight, there’s very little slack left to absorb anything else that goes wrong, calendar-driven slowdowns included. (The customs/VAT-EORI side of that same order is covered in our DDP vs DDU article, linked below — this section is about the production-timing side of it.) A version of this record, anonymized, is documented on our portfolio and proof page.

Checklist before placing a holiday-season order

  1. Check whether your production window touches Chinese New Year, National Day, or Labour Day. Work backward from your event date first (see above), then check the calendar.
  2. Tell us your event or delivery date upfront, not after the quote is agreed — it changes how much buffer is realistic.
  3. Ask for the current status of the specific holiday window, rather than assuming the standard 30-40 day figures apply unchanged.
  4. Don’t plan on rush production as a fallback. It isn’t supported for custom belts at any quantity or time of year.
  5. Separate production time from shipping/customs time in your own planning, since holiday slowdowns can affect both independently.
  6. If you’re ordering the Smart Boxing Machine, confirm current stock status directly if your order falls near a holiday window and you need volume.

Frequently asked questions

Does PunchPowerUp close during Chinese New Year?

We don’t have a published closure schedule to state here. What we can say is that Chinese New Year is a general manufacturing slowdown period across the industry, and that’s the planning risk to account for regardless of any specific closure dates — confirm current status when you request a quote if your timeline is close to it.

Is the 40-day peak-season figure specifically because of Chinese New Year or National Day?

Not confirmed either way in our current records — it may reflect general order volume rather than a fixed calendar link. Treat it as a planning range and ask us to confirm against your specific dates.

Does the Smart Boxing Machine’s 24-hour dispatch get affected by these holidays?

Dispatch itself is from existing stock, so it isn’t tied to a production schedule the way custom belts are. We don’t have published data on whether restocking is affected by these holidays, so confirm directly if you’re ordering in volume near a holiday window.

Can I pay to rush an order if my window overlaps a holiday?

No. Rush production isn’t supported for custom belts, regardless of quantity or time of year.

How much extra buffer should I add if my order overlaps a holiday?

We don’t have a published extra-days figure for this. The safest approach is to flag the overlap when you request a quote and ask for the current assessment against your specific dates, rather than adding an arbitrary number yourself.


Working backward from an event date that might overlap a Chinese holiday? Request a quote with your event date and we’ll confirm the current window.

Editorial note: Product specifications and commercial rules are stated only where verified. Published and updated dates come from the WordPress post record.